Judgment of the General Court of 10 July 2012 — Interspeed v Commission
(Case T-587/10) (1)
(Non-contractual liability - External relations - Call for tenders issued by the EAR concerning work at the Preševo (Serbia) border crossing, the financing of the works and other connected measures - No causal link)
2012/C 250/24
Language of the case: Slovenian
Parties
Applicant: Holding kompanija Interspeed a.d. (Belgrade, Serbia) (represented by: M. Bošnjak, lawyer)
Defendant: EuropeanCommission (represented by: F. Erlbacher and B. Rous, Agents)
Re:
Application for the compensation of damage allegedly resulting from works carried out at the Preševo (Serbia) border crossing under a contract financed by the EAR.
Operative part of the judgment
The Court:
1.
Dismisses the action;
2.
Order Holding kompanija Interspeed a.d to bear its own costs and to pay those incurred by the European Commission.