Official Journal of the European Union
C 48/51
Order of the President of the General Court of 4 December 2015 — E-Control v ACER
(Case T-671/15 R)
((Application for interim measures - Opinion on the compliance of national regulatory authorities’ decisions approving the methods of cross-border electricity transmission capacity - Application for suspension of operation of a measure - Infringement of the procedural requirements - Inadmissibility))
(2016/C 048/59)
Language of the case: English
Parties
Applicant: Energie-Control Austria für die Regulierung der Elektrizitäts- und Erdgaswirtschaft (E-Control) (Vienna, Austria) (represented by: F. Schuhmacher, lawyer)
Defendant: Agency for the Cooperation of Energy Regulators (ACER)
Re:
Application for suspension of operation of Opinion of the Agency for the Cooperation of Energy Regulators No 09/2015 of 23 September 2015 on the compliance of national regulatory authorities’ decisions approving the methods of allocation of cross-border transmission capacity in the Central-East Europe region with Regulation (EC) No 714/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation (EC) No 1228/2003 (OJ 2009 L 211, p. 15), and the guidelines on the management and allocation of available transfer capacity of interconnections between national systems contained in Annex I thereto.
Operative part of the order
1.
The application for interim measures is dismissed.
2.
The costs are reserved.