5.11.2018
EN
Official Journal of the European Union
C 399/37
Order of the President of the General Court of 27 August 2018 — Boyer v Wallis and Futuna
(Case T-475/18 R)
((Interim measures - Public contracts - Application for interim measures - Inadmissibility))
(2018/C 399/50)
Language of the case: French
Parties
Applicant: Boyer (Papeete, France) (represented by T. Dal Farra, lawyer)
Defendant: Territory of the Wallis and Futuna Islands (France)
Re:
Application based on Articles 278 TFEU and 279 TFEU seeking, first, suspension of the operation of the decision of the Territory of the Wallis and Futuna Islands by which it rejected the applicant’s tender and awarded the works contract for construction of a commercial marine dock in Leava (France) to another tenderer, and, second, to suspend the signature of the relevant contract.
Operative part of the order
1.
The application for interim measures is dismissed.
2.
The costs are reserved.