Case T-299/18: Action brought on 16 May 2018 — Strabag Belgium v Parliament
C2592018EN4110120180516EN0056411422
Action brought on 16 May 2018 — Strabag Belgium v Parliament
(Case T-299/18)2018/C 259/56Language of the case: French
Parties
Applicant: Strabag Belgium (Antwerp, Belgium) (represented by: M. Schoups, K. Lemmens and M. Lahbib, lawyers)
Defendant: European Parliament
Form of order sought
The applicant claims that the Court should:
—
declare the present application for annulment admissible and well founded;
—
consequently, annul (i) the decision of 19 April 2018 confirming the decision of the European Parliament of 24 November 2017 to award the framework contract for general contractor works in the European Parliament buildings in Brussels (Call for tenders No 06/D20/2017/M036) to five tenderers other than Strabag Belgium SA and not to the latter undertaking, and (ii) the tender analysis report (addendum) drafted on 26 March 2018 by the evaluation committee appointed by the responsible authorising officer;
—
order the European Parliament to pay all of the costs, including procedural compensation.
Pleas in law and main arguments
In support of the action, the applicant relies on a single plea in law,